Project Progress

Vita Perla & Vita Serenity

Project Progress

You can scroll horizontally to see the stages. You can scroll from the final images to the beginning images of the project. The timing is in chronological order from the end to the beginning.

October 10
2025
PVC and Windows are being installed

Phase 2 PVC and glass installation has started starting from Block B. (Vita Serenity)

September 28
2025
Roof operations underway

Phase 2 Roofing of the remaining blocks is in progress (Vita Serenity)

September 7
2025
Outdoor pool infrastructure works continue

Phase 2 Infrastructure works for the outdoor pool are underway (Vita Serenity)

August 24
2025
Facade works continue at full speed

Phase 2 Exterior facade operations continue at full speed. Scaffolding has started to be dismantled in the completed blocks. (Vita Serenity)

August 05
2025
Roof operations are about to be completed

Phase 2 Roof operations are about to be finalized, only 2 blocks left (Vita Serenity)

July 20
2025
Work for the pool is about to be completed

Stage 2 pool floor has been shaped accordingly and works are about to be completed. (Vita Serenity)

July 01
2025
Underfloor Heating System is Completed

For Phase 2, underfloor heating systems are about to be completed. Facade works are also continuing rapidly. (Vita Serenity)

June 16th
2025
Phase 2 Exterior Facade Works Are Underway

For Phase 2, exterior facade works are continuing at full speed. Scaffolding installations continue. (Vita Serenity)

June 1
2025
Stage 1 Completed 👏

Phase 1 has been successfully completed. As Seraş Construction, we wish all our residents a healthy, peaceful and enjoyable life. (Vita Perla)

May 21
2025
Stage 1 Parking Lot Painting Completed

Parking lot painting for Phase 1 has been completed, there are only a few days left until the completion of Phase 1. (Vita Perla)

May 10
2025
Phase 2 Block B Painting Completed

Phase 2 Block B exterior façade works were completed. Scaffolding dismantled (Vita Serenity)

April 30th
2025
Phase 1 Playground Area Completed
  1. Stage Children's playground and basketball court completed. Painting works for the parking lot are ongoing. (Vita Perla)
April 15th
2025
Stage 2 Roof Insulation Completed

For Phase 2, roof insulation processes have been meticulously completed (Vita Serenity)

March 20
2025
Phase 1 Landscaping Works Completed

Landscaping works for Phase 1 have come to an end. Construction of Children's Park and Basketball Court has started. (Vita Perla)

March 7
2025
Phase 1 Pool Completed

Phase 1 Pool operations completed. The pool was filled (Vita Perla)

February 15
2025
Phase 1 Landscaping Completed

Landscaping for Phase 1 has been completed. Infrastructure work for the pool has been completed. (Vita Perla)

February 06
2025
Phase 1 Signage Completed

Signage for Stage 1 has been completed. The pool has been cleaned. Our apartments are being made ready for delivery. (Vita Perla)

January 21
2025
Phase 2 Roof Operations are Completed

Phase 2 roofing works are nearing the end (Vita Serenity)

January 12
2025
Parking Lot Stones are Completed

For Phase 1, the stones laid at the entrance of the parking lot and the stones laid in the landscape section are about to be finished. (Vita Perla)

January 2
2025
Signage Preparations are Underway

Phase 1 signage preparations are underway. Landscaping works are about to be completed. (Vita Perla)

December 24th
2024
Phase 1 Landscaping Works

The countdown for Phase 1 has begun. Landscaping works are being resumed. Walking paths and garden area markings are about to be completed. (Vita Perla)

December 18
2024
Stage 2 Roof Operations

Roofing for Phase 2 is in full swing (Vita Serenity)

December 2
2024
1st Stage Landscaping Work

Phase 1 landscaping works continue from where they left off. The ground has been made favorable for the plants. Planting process for plants has started. (Vita Perla)

November 20
2024
Stage 2 Decking Works Completed

In the 2nd stage, the deck operations in the blocks have ended. Work continues on the exterior facade. (Vita Serenity)

November 11th
2024
Phase 1 Pool Work Completed

Phase 1 pool preparations have been completed and landscaping works have begun (Vita Perla)

October 25
2024
Phase 1 Sample Apartment Preparations

Phase 1's sample apartments are almost completed. The apartment in question is 3+1. (Vita Perla)

October 18
2024
Phase 1 Landscaping Works

Landscaping preparations for Phase 1 have been completed and work has begun. Preparations have started for the sample apartment (Vita Perla)

October 7
2024
Stage 2 Decking Works

Phase 2's last floor for Block G and Tower for Block F have also been completed. The work on the last deck is nearing completion. (Vita Serenity)

September 17
2024
Stage 2 Pool Works

Phase 2's outdoor pool works continue at full speed. 1.Kulevinch dismantling has been completed (Vita Serenity)

September 11th
2024
I Block 9.70 Flooring

Phase 2's I Block's deck works are in progress (Vita Serenity)

July 28
2024
Stage 1 Isolation Works

Stage 1's insulation works are ongoing. Pool surround arrangements have started. (Vita Perla)

July 17
2024
2nd Stage C Block Last Slab

Phase 2's Block C's last slab has been completed. Work on the remaining blocks has been accelerated. (Vita Serenity)

July 13
2024
Final touches completed

Phase 1 is about to be completed, work has been focused on Phase 2, the big block has been completed, work programs for other blocks have been updated. (Vita Perla & Vita Serenity)

June 29th
2024
Dismantling of Scaffolds Started

For Phase 1, renovations continue rapidly. The scaffolding of some blocks has been dismantled. Ceramic workmanship has been completed and sample flats continue to be built. (Vita Perla)

June 18th
2024
Construction of Remaining Blocks Started

2.Etap'taki bekleyen blokların yapım sürecine başlanıldı. Zemin Döşeme işlemleri devam ediyor. 1.Etap'ın Dış cephesinin seramik işçiliklerinin %85'i tamamlandı. Numune daireler hazırlanmaya başlandı. (Vita Perla & Vita Serenity)

June 7
2024
3rd Floor Concrete Pouring Started

Preparations for pouring concrete on the 3rd floors of the blocks under construction in Phase 2 have been completed. (Vita Serenity)

May 27th
2024
Exterior Facade Almost Finished

Phase 1's exterior facade is almost finished. Ceramic work has started. (Vita Perla)

May 3
2024
Blocks are in Full Speed

Phase 2 blocks are in full swing (Vita Serenity)

April 20
2024
Floor Laying Continues

Phase 2's Block D flooring and concrete pouring operations are ongoing. Phase 1 (Vita Perla) roofing and insulation completed (Vita Perla-Vita Serenity)

March 28th
2024
Columns of Blocks Ready

The columns of the other blocks have been made ready for floor operations. (Vita Serenity)

February 19
2024
B Block 2nd Floor Concrete Process Completed

2nd floor concrete pouring of Block B has been completed (Vita Serenity)

February 1st
2024
Roofing Process Nearing Completion

Phase 1's roof operations are about to be completed. Scaffolding has been installed for exterior works and exterior works have started. (Vita Perla)

January 11
2024
Parking Lot Completed

Parking lot infrastructure has been completed. The ground has been made available for the blocks. Work continues at full speed. (Vita Serenity)

December 27
2023
Roofing Process Continues

Phase 1 roofs are ready (Vita Perla)

November 17th
2023
2. Tower Crane Ready

2.Tower crane has been installed and the work is in full swing day & night (Vita Serenity)

November 6
2023
4th floors are almost finished

The 4th floors have also been concreted. The rough construction of the blocks with the roofs is about to be completed. (Vita Perla)

October 20
2023
Tower Crane Installed

Our 1st tower crane for Serenity has been installed. The process of laying iron on the ground continues. (Vita Serenity)

September 22
2023
Serenity Floor Concrete Poured

The prepared ground concrete has been successfully poured and the foundation is now solidly prepared. Work continues at full speed (Vita Serenity)

August 30th
2023
Serenity Foundation Preparations Completed

Happy August 30 Victory Day (Vita Serenity)

August 24
2023
Concrete Pouring Completed

2nd floor concrete pouring completed (Vita Perla)

July 27
2023
2nd floors are being prepared for concrete

After the 1st floors, preparations for pouring concrete for the 2nd floors continue. Serenity's excavation works are over (Vita Perla & Vita Serenity)

July 3
2023
Foundation Work Started for Serenity

After measuring and marking the Serenity site, excavation work for the foundation began. (Vita Serenity)

June 14th
2023
Floor Started to Be Erected

After the foundation was strengthened, the floor was started to be built on the columns and the bars were laid. Ready for concrete (Vita Perla)

May 19th
2023
Parking Lot Completed

Happy May 19th Youth and Sports Day. Parking infrastructure is ready (Vita Perla)

April 13th
2023
Rebars Preparing for Concrete

Rebars laid on the ground are being prepared for concrete pouring. (Vita Perla)

March 22
2023
Floor Completed

Ground works have been completed. Work continues at full speed. (Vita Perla)

February 21
2023
Ground Work Continues

Work continues in the evening (Vita Perla)

February 17th
2023
Groundwork Prepared

The concrete floor is perfectly finished (Vita Perla)

January 29th
2023
Floor Concrete Poured

The ground is being filled with concrete.(Vita Perla)

January 4
2023
Excavation Continues

After the site was identified, excavation work began. (Vita Perla)

December 21
2022
Excavation Begins

The first phase of the project, Vita Perla, is underway.(Vita Perla)

December 21
2022
Project Started

Vita Perla & Vita Serenity project started.

Stage 1 Vita Perla

Stage 2 Vita Serenity

Project Status

Progress Overall

Vita PERLA 0
Vita SERENITY 0

Vita Perla & Vita Serenity is a Seraş Construction Project. 

Sales of our project are made from our head office, we are waiting for you to our office for detailed information.

Central Office Contact
Project Address
Select the fields to be shown. Others will be hidden. Drag and drop to rearrange the order.
  • Image
  • SKU
  • Rating
  • Price
  • Stock
  • Availability
  • Add to cart
  • Description
  • Content
  • Weight
  • Dimensions
  • Additional information
Click outside to hide the comparison bar
Compare