Project Progress
You can scroll horizontally to see the stages. You can scroll from the final images to the beginning images of the project. The timing is in chronological order from the end to the beginning.

Phase 2 PVC and glass installation has started starting from Block B. (Vita Serenity)

Phase 2 Roofing of the remaining blocks is in progress (Vita Serenity)

Phase 2 Infrastructure works for the outdoor pool are underway (Vita Serenity)

Phase 2 Exterior facade operations continue at full speed. Scaffolding has started to be dismantled in the completed blocks. (Vita Serenity)

Phase 2 Roof operations are about to be finalized, only 2 blocks left (Vita Serenity)

Stage 2 pool floor has been shaped accordingly and works are about to be completed. (Vita Serenity)

For Phase 2, underfloor heating systems are about to be completed. Facade works are also continuing rapidly. (Vita Serenity)

For Phase 2, exterior facade works are continuing at full speed. Scaffolding installations continue. (Vita Serenity)

Phase 1 has been successfully completed. As Seraş Construction, we wish all our residents a healthy, peaceful and enjoyable life. (Vita Perla)

Parking lot painting for Phase 1 has been completed, there are only a few days left until the completion of Phase 1. (Vita Perla)

Phase 2 Block B exterior façade works were completed. Scaffolding dismantled (Vita Serenity)

- Stage Children's playground and basketball court completed. Painting works for the parking lot are ongoing. (Vita Perla)

For Phase 2, roof insulation processes have been meticulously completed (Vita Serenity)

Landscaping works for Phase 1 have come to an end. Construction of Children's Park and Basketball Court has started. (Vita Perla)

Phase 1 Pool operations completed. The pool was filled (Vita Perla)

Landscaping for Phase 1 has been completed. Infrastructure work for the pool has been completed. (Vita Perla)

Signage for Stage 1 has been completed. The pool has been cleaned. Our apartments are being made ready for delivery. (Vita Perla)

Phase 2 roofing works are nearing the end (Vita Serenity)

For Phase 1, the stones laid at the entrance of the parking lot and the stones laid in the landscape section are about to be finished. (Vita Perla)

Phase 1 signage preparations are underway. Landscaping works are about to be completed. (Vita Perla)

The countdown for Phase 1 has begun. Landscaping works are being resumed. Walking paths and garden area markings are about to be completed. (Vita Perla)

Roofing for Phase 2 is in full swing (Vita Serenity)

Phase 1 landscaping works continue from where they left off. The ground has been made favorable for the plants. Planting process for plants has started. (Vita Perla)

In the 2nd stage, the deck operations in the blocks have ended. Work continues on the exterior facade. (Vita Serenity)

Phase 1 pool preparations have been completed and landscaping works have begun (Vita Perla)

Phase 1's sample apartments are almost completed. The apartment in question is 3+1. (Vita Perla)

Landscaping preparations for Phase 1 have been completed and work has begun. Preparations have started for the sample apartment (Vita Perla)

Phase 2's last floor for Block G and Tower for Block F have also been completed. The work on the last deck is nearing completion. (Vita Serenity)

Phase 2's outdoor pool works continue at full speed. 1.Kulevinch dismantling has been completed (Vita Serenity)

Phase 2's I Block's deck works are in progress (Vita Serenity)

Stage 1's insulation works are ongoing. Pool surround arrangements have started. (Vita Perla)

Phase 2's Block C's last slab has been completed. Work on the remaining blocks has been accelerated. (Vita Serenity)

Phase 1 is about to be completed, work has been focused on Phase 2, the big block has been completed, work programs for other blocks have been updated. (Vita Perla & Vita Serenity)

For Phase 1, renovations continue rapidly. The scaffolding of some blocks has been dismantled. Ceramic workmanship has been completed and sample flats continue to be built. (Vita Perla)

2.Etap'taki bekleyen blokların yapım sürecine başlanıldı. Zemin Döşeme işlemleri devam ediyor. 1.Etap'ın Dış cephesinin seramik işçiliklerinin %85'i tamamlandı. Numune daireler hazırlanmaya başlandı. (Vita Perla & Vita Serenity)

Preparations for pouring concrete on the 3rd floors of the blocks under construction in Phase 2 have been completed. (Vita Serenity)

Phase 1's exterior facade is almost finished. Ceramic work has started. (Vita Perla)

Phase 2 blocks are in full swing (Vita Serenity)

Phase 2's Block D flooring and concrete pouring operations are ongoing. Phase 1 (Vita Perla) roofing and insulation completed (Vita Perla-Vita Serenity)

The columns of the other blocks have been made ready for floor operations. (Vita Serenity)

2nd floor concrete pouring of Block B has been completed (Vita Serenity)

Phase 1's roof operations are about to be completed. Scaffolding has been installed for exterior works and exterior works have started. (Vita Perla)

Parking lot infrastructure has been completed. The ground has been made available for the blocks. Work continues at full speed. (Vita Serenity)

Phase 1 roofs are ready (Vita Perla)

2.Tower crane has been installed and the work is in full swing day & night (Vita Serenity)

The 4th floors have also been concreted. The rough construction of the blocks with the roofs is about to be completed. (Vita Perla)

Our 1st tower crane for Serenity has been installed. The process of laying iron on the ground continues. (Vita Serenity)

The prepared ground concrete has been successfully poured and the foundation is now solidly prepared. Work continues at full speed (Vita Serenity)

Happy August 30 Victory Day (Vita Serenity)

2nd floor concrete pouring completed (Vita Perla)

After the 1st floors, preparations for pouring concrete for the 2nd floors continue. Serenity's excavation works are over (Vita Perla & Vita Serenity)

After measuring and marking the Serenity site, excavation work for the foundation began. (Vita Serenity)

After the foundation was strengthened, the floor was started to be built on the columns and the bars were laid. Ready for concrete (Vita Perla)

Happy May 19th Youth and Sports Day. Parking infrastructure is ready (Vita Perla)

Rebars laid on the ground are being prepared for concrete pouring. (Vita Perla)

Ground works have been completed. Work continues at full speed. (Vita Perla)

Work continues in the evening (Vita Perla)

The concrete floor is perfectly finished (Vita Perla)

The ground is being filled with concrete.(Vita Perla)

After the site was identified, excavation work began. (Vita Perla)

The first phase of the project, Vita Perla, is underway.(Vita Perla)

Vita Perla & Vita Serenity project started.
Stage 1 Vita Perla
Stage 2 Vita Serenity